Considering 15 sqm of work for 2 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Laqure spray polishing Paint | 1 | liter | 580 | litre | 580 | 580 | |
| 2 | Painter Painter/Operator | 0.75 | no | 700 | per day | 700 | 525 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 4 | Hire charge of paint spray machine Hire charge of spray machine | 0.75 | day | 700 | per day | 700 | 525 | |
| 5 | Ordinary labour Preparation of surface | 1 | LS | 550 | per day | 171.88 | 171.88 | |
| Sub-Total | 2214.38 | |||||||
| Contractor's Profit | 10% | 0.1 | 221.44 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 77.5 | |||||
| Total | 2513.32 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 203.78 | ||||
| Grand Total | 2717.1 | |||||||
| Rate per sqm | 181.13 | |||||||
| Rate per sqm | 181.13 | |||||||