Considering 10 sqm of work for 1 coat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Standard synthetic enamel paint Paint | 0.63 | liter | 220 | per litre | 220 | 138.6 | |
| 2 | Thinner for oil-based paint (turpentine) for general purpose Thinner | 0.63 | liter | 131 | per litre | 131 | 82.53 | |
| 3 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Scaffolding, sundries, local carriage etc. | 1 | LS | 550 | per day | 55 | 55 | |
| 6 | Ordinary labour Cleaning old surface in/c sand paper etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 956.13 | |||||||
| Contractor's Profit | 10% | 0.1 | 95.61 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.46 | |||||
| Total | 1085.2 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 87.99 | ||||
| Grand Total | 1173.19 | |||||||
| Rate per sqm | 117.3 | |||||||