32.53 Renewing of painting to C.I. Roof with red corrugal paint: 2 coats

Considering 10 sqm of work for 2 coats

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Anti corrosive red oxide paint Paint 0.91 liter 180 per litre 180 163.8
2 Thinner for anti corrosive red oxide paint Thinner 0.91 liter 120 per litre 120 109.2
3 Painter Painter 0.75 no 700 per day 700 525
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.75 no 550 per day 550 412.5
5 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 55 55
6 Ordinary labour Cleaning old surface in/c sand paper etc. 1 LS 550 per day 55 55
Sub-Total 1320.5
Contractor's Profit 10% 0.1 132.05
Contractor's Overhead Expenses 3.5% 0.035 46.22
Total 1498.77
Add VAT with adjustment factor. 1.08108 7.5% 0.075 121.52
Grand Total 1620.29
Rate per sqm 162
Rate per sqm 162