Breakup

32.54.1 Renewing earth oiling with solignum or equivalent materials: 1 coat

Considering 10 sqm of work for 1 coat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthoil Earth-oil 2 kg 55 kg 55 110
2 Painter Painter 0.5 no 700 per day 700 350
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.5 no 550 per day 550 275
4 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 27.5 27.5
5 Ordinary labour Cleaning old surface 1 LS 550 per day 27.5 27.5
Sub-Total 790
Contractor's Profit 10% 0.1 79
Contractor's Overhead Expenses 3.5% 0.035 27.65
Total 896.65
Add VAT with adjustment factor. 1.08108 7.5% 0.075 72.7
Grand Total 969.35
Rate per sqm 96.9
Rate per sqm 96.9