Breakup

32.54.2 Renewing earth oiling with solignum or equivalent materials: 2 coat

Considering 10 sqm of work for 2 coats

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthoil Earth-oil 3.5 kg 55 kg 55 192.5
2 Painter Painter 0.75 no 700 per day 700 525
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.75 no 550 per day 550 412.5
4 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 27.5 27.5
5 Ordinary labour Cleaning old surface 1 LS 550 per day 27.5 27.5
Sub-Total 1185
Contractor's Profit 10% 0.1 118.5
Contractor's Overhead Expenses 3.5% 0.035 41.48
Total 1344.98
Add VAT with adjustment factor. 1.08108 7.5% 0.075 109.05
Grand Total 1454.03
Rate per sqm 145.4
Rate per sqm 145.4