Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Wood varnishing: Yacht ( alkyd based) Varnish | 0.7 | liter | 280 | per litre | 280 | 196 | |
| 2 | Thinner for alkyd based wood varnishing Thinner | 0.64 | liter | 131 | per litre | 131 | 83.84 | |
| 3 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Scaffolding, sundries, local carriage, markin cloth etc. | 1 | LS | 550 | per day | 22 | 22 | |
| 6 | Ordinary labour Cleaning old surface, sand paper | 1 | LS | 550 | per day | 22 | 22 | |
| Sub-Total | 948.84 | |||||||
| Contractor's Profit | 10% | 0.1 | 94.88 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.21 | |||||
| Total | 1076.93 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 87.32 | ||||
| Grand Total | 1164.25 | |||||||
| Rate per sqm | 116.4 | |||||||