Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Wood varnishing: Egg-shell ( alkyd based) Varnish | 0.93 | liter | 280 | per litre | 280 | 260.4 | |
| 2 | Thinner for alkyd based wood varnishing Thinner | 0.24 | liter | 131 | per litre | 131 | 31.44 | |
| 3 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Scaffolding, sundries, local carriage, markin cloth etc. | 1 | LS | 550 | per day | 44 | 44 | |
| 6 | Ordinary labour Cleaning old surface, sand paper | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1004.84 | |||||||
| Contractor's Profit | 10% | 0.1 | 100.48 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 35.17 | |||||
| Total | 1140.49 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 92.47 | ||||
| Grand Total | 1232.96 | |||||||
| Rate per sqm | 123.3 | |||||||
| Rate per sqm | 123.3 | |||||||