Breakup

32.55.2 Renewing of wood varnishing with varnish (egg-shell)

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Wood varnishing: Egg-shell ( alkyd based) Varnish 0.93 liter 280 per litre 280 260.4
2 Thinner for alkyd based wood varnishing Thinner 0.24 liter 131 per litre 131 31.44
3 Painter Painter 0.5 no 700 per day 700 350
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.5 no 550 per day 550 275
5 Ordinary labour Scaffolding, sundries, local carriage, markin cloth etc. 1 LS 550 per day 44 44
6 Ordinary labour Cleaning old surface, sand paper 1 LS 550 per day 44 44
Sub-Total 1004.84
Contractor's Profit 10% 0.1 100.48
Contractor's Overhead Expenses 3.5% 0.035 35.17
Total 1140.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 92.47
Grand Total 1232.96
Rate per sqm 123.3
Rate per sqm 123.3