Breakup

32.56 Scrapping of old paint from wood

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.75 no 550 per day 550 412.5
2 Ordinary labour Scaffolding, sundries,T & P, sand paper etc. 1 LS 550 per day 27.5 27.5
Sub-Total 440
Contractor's Profit 10% 0.1 44
Contractor's Overhead Expenses 3.5% 0.035 15.4
Total 499.4
Add VAT with adjustment factor. 1.08108 7.5% 0.075 40.49
Grand Total 539.89
Rate per sqm 54
Rate per sqm 54