Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 2 | Ordinary labour Scaffolding, sundries,T & P, sand paper etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 440 | |||||||
| Contractor's Profit | 10% | 0.1 | 44 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 15.4 | |||||
| Total | 499.4 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 40.49 | ||||
| Grand Total | 539.89 | |||||||
| Rate per sqm | 54 | |||||||
| Rate per sqm | 54 | |||||||