Breakup

32.57 Scrapping of old mosses from wall and roof

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.45 no 550 per day 550 247.5
2 Ordinary labour Scaffolding, sundries,T & P, sand paper etc. 1 LS 550 per day 33 33
Sub-Total 280.5
Contractor's Profit 10% 0.1 28.05
Contractor's Overhead Expenses 3.5% 0.035 9.82
Total 318.37
Add VAT with adjustment factor. 1.08108 7.5% 0.075 25.81
Grand Total 344.18
Rate per sqm 34.4
Rate per sqm 34.4