Breakup

32.60 Stopping of roof leakage of C.I. sheet roof with putty

Considering 10 sqm work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.2 no 550 per day 550 110
2 Ordinary labour Labour 0.2 no 550 per day 550 110
3 Putty Putty 0.25 kg 107 per kg 107 26.75
4 Ordinary labour Sundries 1 LS 550 per day 11 11
Sub-Total 257.75
Contractor's Profit 10% 0.1 25.78
Contractor's Overhead Expenses 3.5% 0.035 9.02
Total 292.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 23.72
Grand Total 316.27
Rate per sqm 31.6
Rate per sqm 31.6