Considering 10 sqm work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 0.2 | no | 550 | per day | 550 | 110 | |
| 2 | Ordinary labour Labour | 0.2 | no | 550 | per day | 550 | 110 | |
| 3 | Putty Putty | 0.25 | kg | 107 | per kg | 107 | 26.75 | |
| 4 | Ordinary labour Sundries | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 257.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 25.78 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9.02 | |||||
| Total | 292.55 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 23.72 | ||||
| Grand Total | 316.27 | |||||||
| Rate per sqm | 31.6 | |||||||
| Rate per sqm | 31.6 | |||||||