Breakup

32.61 Labour for taking out C.I. sheet roofing

Considering 10 sqm work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.25 no 700 per day 700 175
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.25 no 550 per day 550 137.5
3 Ordinary labour Sundries 1 LS 550 per day 11 11
Sub-Total 323.5
Contractor's Profit 10% 0.1 32.35
Contractor's Overhead Expenses 3.5% 0.035 11.32
Total 367.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 29.77
Grand Total 396.94
Rate per sqm 39.7
Rate per sqm 39.7