Breakup

32.62 Labour for taking out and refitting of old G.I. Ridge/valley

Considering 1.38 meter long

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.1 no 700 per day 700 70
2 Ordinary labour Labour 0.1 no 550 per day 550 55
3 Ordinary labour Washer, nuts & bolt etc. 1 LS 550 per day 44 44
4 Ordinary labour Sundries 1 LS 550 per day 11 11
Sub-Total 180
Contractor's Profit 10% 0.1 18
Contractor's Overhead Expenses 3.5% 0.035 6.3
Total 204.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 16.56
Grand Total 220.86
Rate per meter 160.14
Rate per meter 160.14
Help