Breakup

32.63 Labour for C.I. Sheet roofing including supply of limpet, washer, screws, putty etc.

Considering 1 sqm work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Labour, scaffolding, washer, putty etc. 1 LS 550 per day 103.13 103.13
Sub-Total 103.13
Contractor's Profit 10% 0.1 10.31
Contractor's Overhead Expenses 3.5% 0.035 3.61
Total 117.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 9.49
Grand Total 126.54
Rate per sqm 127
Rate per sqm 127