Breakup

32.67 Labour charge for tightening of old loose barbed wire fencing

Considering 30 m work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.08 no 600 per day 600 48
2 Ordinary labour Nails, wire and sundries 1 LS 550 per day 11 11
Sub-Total 59
Contractor's Profit 10% 0.1 5.9
Contractor's Overhead Expenses 3.5% 0.035 2.07
Total 66.97
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5.43
Grand Total 72.4
Rate per meter 2.4
Rate per meter 2.4