Considering 30 m work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.08 | no | 600 | per day | 600 | 48 | |
| 2 | Ordinary labour Nails, wire and sundries | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 59 | |||||||
| Contractor's Profit | 10% | 0.1 | 5.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.07 | |||||
| Total | 66.97 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5.43 | ||||
| Grand Total | 72.4 | |||||||
| Rate per meter | 2.4 | |||||||
| Rate per meter | 2.4 | |||||||