Considering 1 No. clamp
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 300 long clamp: Iron 300 mm long clamp | 1 | no | 25 | each | 25 | 25 | |
| 2 | Plain concrete (1:2:4) with brick chips C.C. (1:2:4) with brick-chips Item No. 3.5.2 | 0.0056 | cum | 20151.67 | % cft | 7109.51 | 39.81 | |
| 3 | Ordinary labour Labour charge | 1 | LS | 550 | per day | 22 | 22 | |
| Sub-Total | 86.81 | |||||||
| Contractor's Profit | 10% | 0.1 | 8.68 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.04 | |||||
| Total | 98.53 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 7.99 | ||||
| Grand Total | 106.52 | |||||||
| Rate per no | 107 | |||||||
| Rate per each | 107 | |||||||