Breakup

32.68 Renewing, supplying and fitting-fixing of 300 mm long F.I. Clamp in CC (1:2:4)

Considering 1 No. clamp

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 300 long clamp: Iron 300 mm long clamp 1 no 25 each 25 25
2 Plain concrete (1:2:4) with brick chips C.C. (1:2:4) with brick-chips Item No. 3.5.2 0.0056 cum 20151.67 % cft 7109.51 39.81
3 Ordinary labour Labour charge 1 LS 550 per day 22 22
Sub-Total 86.81
Contractor's Profit 10% 0.1 8.68
Contractor's Overhead Expenses 3.5% 0.035 3.04
Total 98.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7.99
Grand Total 106.52
Rate per no 107
Rate per each 107