Considering 100 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Labour for removing jungles | 0.333333333 | no | 550 | per day | 550 | 183.33 | |
| 2 | Ordinary labour Labour for cutting light jungles | 0.5 | no | 550 | per day | 550 | 275 | |
| 3 | Ordinary labour Tools and plant, incidental, sundries etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| Sub-Total | 540.83 | |||||||
| Contractor's Profit | 10% | 0.1 | 54.08 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 18.93 | |||||
| Total | 613.84 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 49.77 | ||||
| Grand Total | 663.61 | |||||||
| Rate per sqm | 6.64 | |||||||
| Rate per sqm | 6.64 | |||||||