Considering 1 No. tub
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 250 mm size earthen tub Cost of of 250mmsize earthen tub including carriage etc. | 1 | no | 50 | each | 50 | 50 | |
| Sub-Total | 50 | |||||||
| Contractor's Profit | 10% | 0.1 | 5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1.75 | |||||
| Total | 56.75 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 4.6 | ||||
| Grand Total | 61.35 | |||||||
| Rate per each | 61 | |||||||
| Rate per each | 61 | |||||||