32.71.12 Supply of T. S. P.

Considering 1 kg

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Triple super phosphate (TSP) Cost of fertilizer in/c carriage 1 kg 30 per kg 30 30
Sub-Total 30
Contractor's Profit 10% 0.1 3
Contractor's Overhead Expenses 3.5% 0.035 1.05
Total 34.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2.76
Grand Total 36.81
Rate per kg 37
Rate per kg 37