Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hand hoe, 250 mm size Cost of hand hoe | 1 | no | 100 | each | 100 | 100 | |
| Sub-Total | 100 | |||||||
| Contractor's Profit | 10% | 0.1 | 10 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.5 | |||||
| Total | 113.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 9.2 | ||||
| Grand Total | 122.7 | |||||||
| Rate per each | 123 | |||||||
| Rate per each | 123 | |||||||