Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 300 mm size G.I. bucket Cost of G.I. Bucket | 1 | no | 280 | each | 280 | 280 | |
| Sub-Total | 280 | |||||||
| Contractor's Profit | 10% | 0.1 | 28 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9.8 | |||||
| Total | 317.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 25.77 | ||||
| Grand Total | 343.57 | |||||||
| Rate per each | 344 | |||||||
| Rate per each | 344 | |||||||