Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Standard synthetic enamel paint Cost of paint | 1 | LS | 220 | per litre | 11.66 | 11.66 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge | 1 | LS | 550 | per day | 13.75 | 13.75 | |
| 3 | Ordinary labour Tools and plant, sundries etc. | 1 | LS | 550 | per day | 2.75 | 2.75 | |
| Sub-Total | 28.16 | |||||||
| Contractor's Profit | 10% | 0.1 | 2.82 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 0.99 | |||||
| Total | 31.97 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2.59 | ||||
| Grand Total | 34.56 | |||||||
| Rate per each | 35 | |||||||
| Rate per each | 35 | |||||||