Breakup

32.74.1 Labour for picking-up and cleaning damaged bituminous road surface

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Labour 1 nos 550 per day 550 550
2 Ordinary labour Incidental, sundries 1 LS 550 per day 33 33
Sub-Total 583
Contractor's Profit 10% 0.1 58.3
Contractor's Overhead Expenses 3.5% 0.035 20.41
Total 661.71
Add VAT with adjustment factor. 1.08108 7.5% 0.075 53.65
Grand Total 715.36
Rate per sft 7.15
Rate per sqm 76.96