32.74.2 Repairing the potholes of the road by picking up and removing damaged materials with stone chips

Considering 1 cum work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 60/70 grade bitumen for road work Bitumen 100 kg 56000 per M. ton 56 5600
2 Sand (F.M. 2.2) Sand (F.M 2.2) 0.25 cum 5380 per % cft 189.97 47.49
3 19 mm (3/4") down grade crushed stone chips Stone chips 0.9 cum 21804 per % cft 7692.45 6923.2
4 Fire-wood Fire wood 2.7 mnd 220 per mound 220 594
5 Tar boiler Tar boiler 0.5 day 1120 per day 1120 560
6 Vibrating roller Pedestrain (0.5 - 1 ton) Vibrating roller Pedestrain 0.5 - 1 ton capacity 0.5 day 3500 per day 3500 1750
7 Mason / Mosaic mistry Mason 1 nos 700 per day 700 700
8 Skilled labour Skilled labour 4 nos 600 per day 600 2400
9 Ordinary labour Ordinary labour 10 nos 550 per day 550 5500
10 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 24899.69
Contractor's Profit 10% 0.1 2489.97
Contractor's Overhead Expenses 3.5% 0.035 871.49
Total 28261.15
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2291.44
Grand Total 30552.59
Rate per cum 30553
Rate per cum 30553