32.76.1 Supplying timber (unfinished) for repairing in wood works: Garjan/Jam/local Sal

Considering 1 cft unfinished wood (Garjan/Jam/Local Sal)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Garjan/Jam/local Sal Cost of unfinished wood 1 cft 2200 per cft 2200 2200
Sub-Total 2200
Contractor's Profit 10% 0.1 220
Contractor's Overhead Expenses 3.5% 0.035 77
Total 2497
Add VAT with adjustment factor. 1.08108 7.5% 0.075 202.46
Grand Total 2699.46
Rate per cft 2699
Rate per cum 8855.42