Breakup

32.76.2 Supplying timber (unfinished) for repairing in wood works: Jarul

Considering 1 cft unfinished wood (Jarul)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Jarul Cost of unfinished wood 1 cft 1800 per cft 1800 1800
Sub-Total 1800
Contractor's Profit 10% 0.1 180
Contractor's Overhead Expenses 3.5% 0.035 63
Total 2043
Add VAT with adjustment factor. 1.08108 7.5% 0.075 165.65
Grand Total 2208.65
Rate per cft 2209
Rate per cum 7247.73