Considering 1 cft unfinished wood (Shilkorai/Chickrashi)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Silkarai/Chikrashi Cost of unfinished wood | 1 | cft | 2500 | per cft | 2500 | 2500 | |
| Sub-Total | 2500 | |||||||
| Contractor's Profit | 10% | 0.1 | 250 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 87.5 | |||||
| Total | 2837.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 230.07 | ||||
| Grand Total | 3067.57 | |||||||
| Rate per cft | 3068 | |||||||
| Rate per cum | 10066.11 | |||||||