32.76.3 Supplying timber (unfinished) for repairing in wood works: Shilkorai/Chickrashi

Considering 1 cft unfinished wood (Shilkorai/Chickrashi)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Silkarai/Chikrashi Cost of unfinished wood 1 cft 2500 per cft 2500 2500
Sub-Total 2500
Contractor's Profit 10% 0.1 250
Contractor's Overhead Expenses 3.5% 0.035 87.5
Total 2837.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 230.07
Grand Total 3067.57
Rate per cft 3068
Rate per cum 10066.11