32.76.7 Supplying timber (unfinished) for repairing in wood works: Gamari

Considering 1 cft unfinished wood (Gamari)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Gamari Cost of unfinished wood 1 cft 1900 per cft 1900 1900
Sub-Total 1900
Contractor's Profit 10% 0.1 190
Contractor's Overhead Expenses 3.5% 0.035 66.5
Total 2156.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 174.85
Grand Total 2331.35
Rate per cft 2331
Rate per cum 7648.01