Breakup

32.76.9 Supplying timber (unfinished) for repairing in wood works: Loha/Pyiankado

Considering 1 cft unfinished wood (Loha/Pyiankado)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Loha/Pyiankado Cost of unfinished wood 1 cft 2700 per cft 2700 2700
Sub-Total 2700
Contractor's Profit 10% 0.1 270
Contractor's Overhead Expenses 3.5% 0.035 94.5
Total 3064.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 248.47
Grand Total 3312.97
Rate per cft 3313
Rate per cum 10869.95