32.76.11 Supplying timber (unfinished) for repairing in wood works: Ordinary timber (Mehogoni)

Considering 1 cft unfinished wood Ordinary timber (Mehgoni)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mehgani Cost of unfinished wood 1 cft 2000 per cft 2000 2000
Sub-Total 2000
Contractor's Profit 10% 0.1 200
Contractor's Overhead Expenses 3.5% 0.035 70
Total 2270
Add VAT with adjustment factor. 1.08108 7.5% 0.075 184.05
Grand Total 2454.05
Rate per cft 2454
Rate per cum 8051.57