Considering 1 cft unfinished wood Ordinary timber (Mehgoni)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mehgani Cost of unfinished wood | 1 | cft | 2000 | per cft | 2000 | 2000 | |
| Sub-Total | 2000 | |||||||
| Contractor's Profit | 10% | 0.1 | 200 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 70 | |||||
| Total | 2270 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 184.05 | ||||
| Grand Total | 2454.05 | |||||||
| Rate per cft | 2454 | |||||||
| Rate per cum | 8051.57 | |||||||