Breakup

32.77 Labour charge for cleaning, washing, brooming from all heights and stacking of debris at a place beyond plinth area of the the site during execution of repair works as per direction of the engineer-in-charge

Considering 1 cum debris

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Labour for cleaning, washing brooming and internal carrying, stacking etc. 2 nos 550 per day 550 1100
2 Ordinary labour T & P, scaffolding, ladder, sundries etc. 1 LS 550 per day 82.5 82.5
Sub-Total 1182.5
Contractor's Profit 10% 0.1 118.25
Contractor's Overhead Expenses 3.5% 0.035 41.39
Total 1342.14
Add VAT with adjustment factor. 1.08108 7.5% 0.075 108.82
Grand Total 1450.96
Rate per cum 1451
Rate per cum 1451