Considering 1 cum debris
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Labour for cleaning, washing brooming and internal carrying, stacking etc. | 2 | nos | 550 | per day | 550 | 1100 | |
| 2 | Ordinary labour T & P, scaffolding, ladder, sundries etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| Sub-Total | 1182.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 118.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 41.39 | |||||
| Total | 1342.14 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 108.82 | ||||
| Grand Total | 1450.96 | |||||||
| Rate per cum | 1451 | |||||||
| Rate per cum | 1451 | |||||||