32.78 Cleaning, washing, brooming and taking away of debris from the site during and or after the completion of the repair works in all heights by truck or by any other means as per direction of the engineer-in-charge

Considering 3 cum debris

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Cart fare within 5 km Truck fare for 1 trip in/c loading-unloading 1 trip 600 per trip 600 600
2 Ordinary labour Labour for cleaning, washing & brooming 2 nos 550 per day 550 1100
3 Ordinary labour T & P, sundries etc. 1 LS 550 per day 275 275
Sub-Total 1975
Contractor's Profit 10% 0.1 197.5
Contractor's Overhead Expenses 3.5% 0.035 69.13
Total 2241.63
Add VAT with adjustment factor. 1.08108 7.5% 0.075 181.75
Grand Total 2423.38
Rate per cum 807.67
Rate per cum 807.67