Considering 4' - 0" x 4' - 6" = 18 sft size window grill
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Welder Welder | 0.25 | no | 700 | per day | 700 | 175 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to welder | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 3 | Ordinary labour Work shop charge | 1 | LS | 550 | per day | 206.25 | 206.25 | |
| 4 | Electrodes including electricity Welding electrodes | 6 | nos | 10 | each | 10 | 60 | |
| 5 | Ordinary labour Conveyance and carrying | 1 | LS | 550 | per day | 192.5 | 192.5 | |
| 6 | Ordinary labour Dismantling | 1 | LS | 550 | per day | 165 | 165 | |
| 7 | Ordinary labour Hardwares, fittings etc. | 1 | LS | 550 | per day | 51.56 | 51.56 | |
| 8 | Ordinary labour Fitting-fixing in position excluding cost of mending good the damages to walls & concrete | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 1262.81 | |||||||
| Contractor's Profit | 10% | 0.1 | 126.28 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 44.2 | |||||
| Total | 1433.29 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 116.21 | ||||
| Grand Total | 1549.5 | |||||||
| Rate per sft | 86.11 | |||||||
| Rate per sqm | 926.89 | |||||||