Breakup

32.79 Repairing of steel grill/window frame and shutter/stair railing, veranda grill, rolling shutter excluding the cost of steel materials.

Considering 4' - 0" x 4' - 6" = 18 sft size window grill

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Welder Welder 0.25 no 700 per day 700 175
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to welder 0.25 no 550 per day 550 137.5
3 Ordinary labour Work shop charge 1 LS 550 per day 206.25 206.25
4 Electrodes including electricity Welding electrodes 6 nos 10 each 10 60
5 Ordinary labour Conveyance and carrying 1 LS 550 per day 192.5 192.5
6 Ordinary labour Dismantling 1 LS 550 per day 165 165
7 Ordinary labour Hardwares, fittings etc. 1 LS 550 per day 51.56 51.56
8 Ordinary labour Fitting-fixing in position excluding cost of mending good the damages to walls & concrete 1 LS 550 per day 275 275
Sub-Total 1262.81
Contractor's Profit 10% 0.1 126.28
Contractor's Overhead Expenses 3.5% 0.035 44.2
Total 1433.29
Add VAT with adjustment factor. 1.08108 7.5% 0.075 116.21
Grand Total 1549.5
Rate per sft 86.11
Rate per sqm 926.89
Help