32.80.1 40-grade deform bar

Considering use of 1 kg 40-grade deform bar

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 Cost of materials 1 kg 65000 per M. ton 65 65
Sub-Total 65
Contractor's Profit 10% 0.1 6.5
Contractor's Overhead Expenses 3.5% 0.035 2.2800000000000002
Total 73.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5.98
Grand Total 79.76
Rate per kg 80
Rate per kg 80