Considering use of 1 kg M.S. angle, T, and Z - section, Channel etc.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. Cost of materials | 1 | kg | 70000 | per M. ton | 70 | 70 | |
| Sub-Total | 70 | |||||||
| Contractor's Profit | 10% | 0.1 | 7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.45 | |||||
| Total | 79.45 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 6.44 | ||||
| Grand Total | 85.89 | |||||||
| Rate per kg | 86 | |||||||
| Rate per kg | 86 | |||||||