Breakup

32.81 Cleaning and mending good the damages surrounding the mouth of spout/rain water down pipe

Considering 1 No. of spout mouth

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.0810810810810811 no 700 per day 700 56.76
2 Ordinary labour Ordinary labour 0.0810810810810811 no 550 per day 550 44.59
3 Ordinary labour Lime, chips and surki etc. 1 LS 550 per day 30.94 30.94
4 Ordinary labour T & P, sundries etc. 1 LS 550 per day 8.25 8.25
Sub-Total 140.54
Contractor's Profit 10% 0.1 14.05
Contractor's Overhead Expenses 3.5% 0.035 4.92
Total 159.51
Add VAT with adjustment factor. 1.08108 7.5% 0.075 12.93
Grand Total 172.44
Rate per each 172
Rate per each 172