Breakup

32.82 Cleaning rain water down pipe

Considering 30 meter work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
2 Ordinary labour T & P, sundries etc. 1 LS 550 per day 16.5 16.5
Sub-Total 154
Contractor's Profit 10% 0.1 15.4
Contractor's Overhead Expenses 3.5% 0.035 5.39
Total 174.79
Add VAT with adjustment factor. 1.08108 7.5% 0.075 14.17
Grand Total 188.96
Rate per meter 6.3
Rate per meter 6.3