Breakup

32.85 Clearing chocked up masonry surface drain

Considering 30 m long surface drain

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 0.8 no 800 per use 800 640
2 Ordinary labour T & P and sundries 1 LS 550 per day 110 110
Sub-Total 750
Contractor's Profit 10% 0.1 75
Contractor's Overhead Expenses 3.5% 0.035 26.25
Total 851.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 69.02
Grand Total 920.27
Rate per meter 30.67
Rate per meter 30.67