Breakup

32.87.2 20 user septic tank

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 2 use 800 per use 800 1600
2 Cart fare within 5 km Hire charge of cart 1 trip 600 per trip 600 600
3 Ordinary labour T & P, consumables and sundries 1 LS 550 per day 550 550
Sub-Total 2750
Contractor's Profit 10% 0.1 275
Contractor's Overhead Expenses 3.5% 0.035 96.25
Total 3121.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 253.07
Grand Total 3374.32
Rate per each 3374
Rate per each 3374