Breakup

32.87.3 30 user septic tank

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 2.5 use 800 per use 800 2000
2 Cart fare within 5 km Hire charge of cart 1 trip 600 per trip 600 600
3 Ordinary labour T & P, consumables and sundries 1 LS 550 per day 550 550
Sub-Total 3150
Contractor's Profit 10% 0.1 315
Contractor's Overhead Expenses 3.5% 0.035 110.25
Total 3575.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 289.88
Grand Total 3865.13
Rate per each 3865
Rate per each 3865
Help