Breakup

32.87.5 100 user septic tank

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 7 use 800 per use 800 5600
2 Cart fare within 5 km Hire charge of cart 4 trip 600 per trip 600 2400
3 Ordinary labour T & P, consumables and sundries 1 LS 550 per day 550 550
Sub-Total 8550
Contractor's Profit 10% 0.1 855
Contractor's Overhead Expenses 3.5% 0.035 299.25
Total 9704.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 786.83
Grand Total 10491.08
Rate per each 10491
Rate per each 10491
Help