Breakup

32.88 Clearing sludges & night soil from Inspection pit

Considering 1 No. pit

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sweeper for ODD JOB Sweeper for odd job 0.5 use 800 per use 800 400
2 Ordinary labour T & P, consumables and sundries 1 LS 550 per day 27.5 27.5
Sub-Total 427.5
Contractor's Profit 10% 0.1 42.75
Contractor's Overhead Expenses 3.5% 0.035 14.96
Total 485.21
Add VAT with adjustment factor. 1.08108 7.5% 0.075 39.34
Grand Total 524.55
Rate per each 525
Rate per each 525