Considering 30 m long RCC pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Sweeper for ODD JOB Sweeper for odd job | 2.5 | use | 800 | per use | 800 | 2000 | |
| 2 | Cart fare within 5 km Hire charge of cart | 1 | trip | 600 | per trip | 600 | 600 | |
| 3 | Ordinary labour T & P, consumables and sundries | 1 | LS | 550 | per day | 110 | 110 | |
| Sub-Total | 2710 | |||||||
| Contractor's Profit | 10% | 0.1 | 271 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 94.85 | |||||
| Total | 3075.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 249.39 | ||||
| Grand Total | 3325.24 | |||||||
| Rate per meter | 110.83 | |||||||
| Rate per meter | 110.83 | |||||||