Considering 30 m pipe
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Tube-well mistry Tube-well mistry | 2 | nos | 700 | per day | 700 | 1400 | |
| 2 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 3 | Ordinary labour T & P, consumables and sundries | 1 | LS | 550 | per day | 440 | 440 | |
| Sub-Total | 2940 | |||||||
| Contractor's Profit | 10% | 0.1 | 294 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 102.9 | |||||
| Total | 3336.9 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 270.56 | ||||
| Grand Total | 3607.46 | |||||||
| Rate per meter | 120.23 | |||||||
| Rate per meter | 120.23 | |||||||