Considering 1 No. European type commode
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.2 | no | 600 | per day | 600 | 120 | |
| 2 | Ordinary labour T & P and sundries | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 164 | |||||||
| Contractor's Profit | 10% | 0.1 | 16.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5.74 | |||||
| Total | 186.14 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 15.09 | ||||
| Grand Total | 201.23 | |||||||
| Rate per each | 201 | |||||||
| Rate per each | 201 | |||||||