Breakup

32.96 Taking out broken European type Commode

Considering 1 No. European type commode

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.2 no 600 per day 600 120
2 Ordinary labour T & P and sundries 1 LS 550 per day 44 44
Sub-Total 164
Contractor's Profit 10% 0.1 16.4
Contractor's Overhead Expenses 3.5% 0.035 5.74
Total 186.14
Add VAT with adjustment factor. 1.08108 7.5% 0.075 15.09
Grand Total 201.23
Rate per each 201
Rate per each 201