Considering 1 No. C.I. Cistern
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 37 mm dia uPVC pipe 37 mm dia PVC pipe | 2 | rft | 40.5 | per foot | 40.5 | 81 | |
| 2 | Ordinary labour Labour for making hole & fitting-fixing etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 3 | Ordinary labour Cost of mending damage | 1 | LS | 550 | per day | 25.78 | 25.78 | |
| 4 | Ordinary labour Sundries | 1 | LS | 550 | per day | 16.5 | 16.5 | |
| Sub-Total | 205.78 | |||||||
| Contractor's Profit | 10% | 0.1 | 20.58 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 7.2 | |||||
| Total | 233.56 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 18.94 | ||||
| Grand Total | 252.5 | |||||||
| Rate per each | 253 | |||||||
| Rate per each | 253 | |||||||