Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia uPVC pipe 25 mm dia PVC pipe | 1.5 | rft | 27.2 | per foot | 24.48 | 36.72 | |
| 2 | Ordinary labour Labour for making hole & fitting-fixing etc. | 1 | LS | 550 | per day | 110 | 110 | |
| 3 | Ordinary labour Cost of mending damage | 1 | LS | 550 | per day | 44 | 44 | |
| 4 | Ordinary labour Sundries | 1 | LS | 550 | per day | 13.75 | 13.75 | |
| Sub-Total | 204.47 | |||||||
| Contractor's Profit | 10% | 0.1 | 20.45 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 7.16 | |||||
| Total | 232.08 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 18.82 | ||||
| Grand Total | 250.9 | |||||||
| Rate per each | 251 | |||||||