Considering 1 set fittings
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Siphon set for plastic low-down Siphon set for plastic low-down | 1 | set | 438 | set | 438 | 438 | |
| 2 | Plumber Labour charge: Plumber | 0.25 | no | 700 | per day | 700 | 175 | |
| 3 | Ordinary labour Sundries | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 657 | |||||||
| Contractor's Profit | 10% | 0.1 | 65.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 23 | |||||
| Total | 745.7 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 60.46 | ||||
| Grand Total | 806.16 | |||||||
| Rate per each | 806 | |||||||
| Rate per each | 806 | |||||||