Breakup

32.101 250mm and above thick brick work (1:6) in old/unserviceable septic tank

Considering 100 cft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 1100 nos 10000 per % 0 nos 10 11000
2 Sand (F.M. 1.2) Sand (F.M 1.2) in/c wastage 36 cft 1900 per % cft 19 684
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 4 bags 410 per bag 410 1640
4 Head mason / Mosaic head mistry Head mason 0.1 no 800 per day 800 80
5 Mason / Mosaic mistry Mason for odd job 1 no 700 per day 1400 1400
6 Skilled labour Skilled labour for odd job 1 no 600 per day 1200 1200
7 Ordinary labour Ordinary labour for odd job 1 nos 550 per day 1100 1100
8 Ordinary labour Labour for soaking & cleaning bricks 2 nos 550 per day 550 1100
9 Ordinary labour Labour for 7 days curing '@ 1/4 labour per day: 1.7 nos 550 per day 550 935
10 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 275 275
Sub-Total 19414
Contractor's Profit 10% 0.1 1941.4
Contractor's Overhead Expenses 3.5% 0.035 679.49
Total 22034.89
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1786.61
Grand Total 23821.5
Rate per cft 238.22
Rate per cum 8412.74