Breakup

32.103 12 mm plaster (1:4) with neat cement finishing in old/dilapitated septic tank

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 1.2) Sand (F.M. 1.2) 5 cft 1900 per % cft 19 95
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 1.5 bag 410 per bag 410 615
3 Mason / Mosaic mistry Mason for odd job 0.25 no 700 per day 1400 350
4 Skilled labour Skilled labour for odd job 1.25 nos 600 per day 1200 1500
5 Ordinary labour Ordinary labour for odd job 1.25 nos 550 per day 1100 1375
6 Ordinary labour Washing of sand, local carriage, curing, & sundries etc. 1 LS 550 per day 550 550
Sub-Total 4485
Contractor's Profit 10% 0.1 448.5
Contractor's Overhead Expenses 3.5% 0.035 156.98
Total 5090.48
Add VAT with adjustment factor. 1.08108 7.5% 0.075 412.74
Grand Total 5503.22
Rate per sft 55.03
Rate per sqm 592.34