Breakup

32.108 Cleaning over head water reservior and removing the waste to safe place/ distance from building site without affecting the environment etc. All completed as per direction of Engineer- in charge.

Considering- 2000 gallon Reservior, (1 No OHWR)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour a) Skilled labour 1 day 600 per day 600 600
2 Ordinary labour b) Ordinary labour 1 day 550 per day 550 550
3 Bleaching powder c) Bleaching powder 1.25 kg 100 per kg 100 125
4 Detergent powder d) Detergent powder 0.75 kg 120 per kg 120 90
5 e) Sundries, exhaust fan, brush,T & P etc. LS 260
Sub-Total 1625
Contractor's Profit 10% 0.1 162.5
Contractor's Overhead Expenses 3.5% 0.035 56.88
Total 1844.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 149.54
Grand Total 1993.92
Rate per gallon 1
Rate per gallon 1