Considering- 2000 gallon Reservior, (1 No OHWR)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour a) Skilled labour | 1 | day | 600 | per day | 600 | 600 | |
| 2 | Ordinary labour b) Ordinary labour | 1 | day | 550 | per day | 550 | 550 | |
| 3 | Bleaching powder c) Bleaching powder | 1.25 | kg | 100 | per kg | 100 | 125 | |
| 4 | Detergent powder d) Detergent powder | 0.75 | kg | 120 | per kg | 120 | 90 | |
| 5 | e) Sundries, exhaust fan, brush,T & P etc. | LS | 260 | |||||
| Sub-Total | 1625 | |||||||
| Contractor's Profit | 10% | 0.1 | 162.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 56.88 | |||||
| Total | 1844.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 149.54 | ||||
| Grand Total | 1993.92 | |||||||
| Rate per gallon | 1 | |||||||
| Rate per gallon | 1 | |||||||